CIP (Health and Safety)
as of February 15, 2000
| # |
Project/Cost/ Consultant/Contractor
|
Location/ Building |
Project Scope |
Estimated Schedule |
|
33
SK
Jan 24
|
Fire Safety Improvements Phase 1 - Fire
alarm upgrade and provide dorm sprinkler
$1,173,300
DMT Engineers (Consultant)
Stans Contracting, Inc. (Contractor)
|
Theater, Campus Center,
OSS, Business Ed. 346/bookstr., Hale Ikena and Hale Kanilehua |
Providing new fire alarm
system at all buildigns listed. New fire sprinkler system at Hale
Ikena and Kanilehua. New system will be tied to main alarm panel
at Security office. |
99 percent complete except for outstanding
items from Blaise
|
| # |
Project/Cost/ Consultant/Contractor
|
Location/ Building |
Project Scope |
Estimated Schedule |
|
34
SK
Jan 24
|
Fire Safety Improvements Phase 2 - Fire
alarm up-grade and provide dorm sprinkler
$?
Wesley R. Segawa & Associates,
Inc. (Consultant)
|
Hale Kauanoe |
Providing new fire alarm
and sprinkler at Hale Kauanoe. |
Preliminary Design Phase
|
| # |
Project/Cost/ Consultant/Contractor
|
Location/ Building |
Project Scope |
Estimated Schedule |
|
35
LC
Jan 31
|
Hale Kehau Fire Sprinklers and alarm
$500,000
|
Hale Kehau |
Project will improve fire
sprinklers and fire alarm system in Hale Kehau. |
Project initiation
(System wide)
|
| # |
Project/Cost/ Consultant/Contractor
|
Location/ Building |
Project Scope |
Estimated Schedule |
|
36
LC
Jan 31
|
(Health and Safety) - Main Campus Lighting
Improvement
$550,000
|
Various locations |
Project will provide lights
in existing parking lots, walkways in the main campus. |
Project initiation
(System wide)
|
| # |
Project/Cost/ Consultant/Contractor
|
Location/ Building |
Project Scope |
Estimated Schedule |
|
37
JH
Jan 24
|
(Supplemental CIP) - OSS Air Quality
Improvements
$300,000
W.A. Hirai & Associates Inc.
(Consultant)
|
Student Services Bldg.
338 |
Improve air quality of
Student Services Building |
Design Initiated
|
| # |
Project/Cost/ Consultant/Contractor
|
Location/ Building |
Project Scope |
Estimated Schedule |
|
38
LC
Jan 31
|
(Health and Safety) - Theater Catwalk
& Stage balancing sys. Improvement
$350,000
|
Theater |
This project will improve
Theater catwalk and improve work place safety. |
Project initiation
(System wide)
|
| # |
Project/Cost/ Consultant/Contractor
|
Location/ Building |
Project Scope |
Estimated Schedule |
|
39
SK
Jan 24
|
(Health and Safety) - Repair/Replace
Stage Balancing System
$?
(Consultant selection process)
|
Theater |
Replace stage balancing
system at the Theater. |
Consultant selection phase
|
| # |
Project/Cost/ Consultant/Contractor
|
Location/ Building |
Project Scope |
Estimated Schedule |
|
40
SK
Jan 24
|
(Health and Safety) - Electrical up-grade
at Theater
$195,000
M&E Pacific, Inc. (Consultant)
T&T
Electric, Inc. (Contractor)
|
Theater |
Electrical up-grade throughout.
|
Completed.
|
| # |
Project/Cost/ Consultant/Contractor
|
Location/ Building |
Project Scope |
Estimated Schedule |
|
41
LC
Jan 31
|
Lab Safety Improvements
$460,000
|
Life Sciences and Agriculture
labs. |
Project will provide Bio-Level
2 lab improvements for Life Sciences and Agriculture labs. |
Project initiation
(System wide)
|
| # |
Project/Cost/ Consultant/Contractor
|
Location/ Building |
Project Scope |
Estimated Schedule |
|
42
SK
Jan 24
|
(Health and Safety) - Asbestos Removal
and Replacement Phase 2
$1,185,000
M&E Pacific, Inc. (Consultant)
QMC Corp. (Contractor)
|
Theater, Bookstore, Wentworth
Hall and covered walkway |
Remove asbestos contained
roofing at Theater and covered walkway and replace with new roofing.
Remove asbestos ceiling at CC Marriott dining room, Bookstore and
Wentworth Hall and replace with new. |
Completed
|
| # |
Project/Cost/ Consultant/Contractor
|
Location/ Building |
Project Scope |
Estimated Schedule |
|
43
SK
Jan 24
|
(Health and Safety) - Asbestos Removal
and Replacement Phase 2B
$82,200
Architechnical Design Assoc. (Consultant)
Site Engineering (Contractor)
|
College Hall room CH5A
and CH11C, PB-8A Rehearsal Room and Chiller Building |
Removal of Asbestos contained flooring
at CH5 and PB-8A Rehearsal room and replace with new.
Removal of asbestos contained transite
panels at CH11C and replacement of doors, lighting, flooring.
Removal of asbestos contained roofing
at Chiller Building and replace with new metal roofing, gutters
and downspouts.
|
CH5, CH11C and PB-8A Rehearsal room
completed.
Chiller Building to start February
/ March and complete June 2000.
|
|