CIP (Health and Safety)
as of February 15, 2000

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

33
SK

Jan 24

Fire Safety Improvements Phase 1 - Fire alarm upgrade and provide dorm sprinkler

$1,173,300

DMT Engineers (Consultant)

Stans Contracting, Inc. (Contractor)

Theater, Campus Center, OSS, Business Ed. 346/bookstr., Hale Ikena and Hale Kanilehua Providing new fire alarm system at all buildigns listed. New fire sprinkler system at Hale Ikena and Kanilehua. New system will be tied to main alarm panel at Security office.

99 percent complete except for outstanding items from Blaise

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

34
SK

Jan 24

Fire Safety Improvements Phase 2 - Fire alarm up-grade and provide dorm sprinkler

$?

Wesley R. Segawa & Associates, Inc. (Consultant)

Hale Kauanoe Providing new fire alarm and sprinkler at Hale Kauanoe.

Preliminary Design Phase

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

35
LC

Jan 31

Hale Kehau Fire Sprinklers and alarm

$500,000

Hale Kehau Project will improve fire sprinklers and fire alarm system in Hale Kehau.

Project initiation

(System wide)

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

36
LC

Jan 31

(Health and Safety) - Main Campus Lighting Improvement

$550,000

Various locations Project will provide lights in existing parking lots, walkways in the main campus.

Project initiation

(System wide)

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

37
JH

Jan 24

(Supplemental CIP) - OSS Air Quality Improvements

$300,000

W.A. Hirai & Associates Inc.

(Consultant)

Student Services Bldg. 338 Improve air quality of Student Services Building

Design Initiated

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

38
LC

Jan 31

(Health and Safety) - Theater Catwalk & Stage balancing sys. Improvement

$350,000

Theater This project will improve Theater catwalk and improve work place safety.

Project initiation

(System wide)

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

39
SK

Jan 24

(Health and Safety) - Repair/Replace Stage Balancing System

$?

(Consultant selection process)

Theater Replace stage balancing system at the Theater.

Consultant selection phase

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

40
SK

Jan 24

(Health and Safety) - Electrical up-grade at Theater

$195,000
M&E Pacific, Inc. (Consultant)
T&T Electric, Inc. (Contractor)

Theater Electrical up-grade throughout.

Completed.

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

41
LC

Jan 31

Lab Safety Improvements

$460,000

Life Sciences and Agriculture labs. Project will provide Bio-Level 2 lab improvements for Life Sciences and Agriculture labs.

Project initiation

(System wide)

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

42
SK

Jan 24

(Health and Safety) - Asbestos Removal and Replacement Phase 2

$1,185,000

M&E Pacific, Inc. (Consultant)

QMC Corp. (Contractor)

Theater, Bookstore, Wentworth Hall and covered walkway Remove asbestos contained roofing at Theater and covered walkway and replace with new roofing. Remove asbestos ceiling at CC Marriott dining room, Bookstore and Wentworth Hall and replace with new.

Completed

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

43
SK

Jan 24

(Health and Safety) - Asbestos Removal and Replacement Phase 2B

$82,200

Architechnical Design Assoc. (Consultant)

Site Engineering (Contractor)

College Hall room CH5A and CH11C, PB-8A Rehearsal Room and Chiller Building

Removal of Asbestos contained flooring at CH5 and PB-8A Rehearsal room and replace with new.

Removal of asbestos contained transite panels at CH11C and replacement of doors, lighting, flooring.

Removal of asbestos contained roofing at Chiller Building and replace with new metal roofing, gutters and downspouts.

CH5, CH11C and PB-8A Rehearsal room completed.

Chiller Building to start February / March and complete June 2000.

 