CIP
as of February 15, 2000

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

1
JH

Jan
24

University Park Phase 2A

$7,500,000

Engineering Concepts, Inc. (Consultant)

M. Sonomura Contracting Co., Inc. (Contractor)

University Park Nowela Street, Nowela Bridge, Campus Center plaza and Kawili Street main entrance Roadway extension from University Park to Kawili Street, new entry to campus, additional parking. 02/2000 completion
# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

2
LC

Jan
31

University Park Phase 2B - Reservoir

$3,250,000

DMT Engineers (Consultant)

Glover Construction (Contractor)

above Komohana portion of University Park This project will provide a reservoir and transmission lines, which are necessary for further development of the University.

Construction

Fall 1999 to Spring 2001

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

3
LC

Jan
31

(Supplemental CIP) - Long Range Plan above Komohana

$375,000

Main Campus, Tech. park This project will provide master plan for the development of 300 plus acres of land above Komohana.

Supplemental Request

(System wide)

 

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

4
LC

Jan 31

(PORK) - University Park Phase 3 - New Road

$2,750,000

University Park This project will provide additional roadway and infrastructure in University Park.

To be lapsed by Governor.

(Pork)

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

5
JH

Jan 24

Utility Grid Phase 1

$3,800,000

Douglas V. MacMahon, Ltd. (Consultant)

Able Electric (Contractor)

Main Campus wide First phase of new utility grid system for the Main Campus.

Construction Completed

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

6
JH

Jan 24

Utility Grid Phase 1B

$500,000

Douglas V. MacMahon, Ltd. (Consultant)

Back of dormitory and portion of main campus Next phase of Utility Grid work.

Preliminary Design Phase

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

7
JH

Jan 24

Utility Grid Phase 1C

$150,000

Douglas V. MacMahon, Ltd. (Consultant)

New Switchgear at Main Campus Build a permanent enclosure around newly installed switchgear.

Final Design Phase

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

8
LC

Jan 24

(Supplemental CIP) - Utility Grid Phase 2

$3,000,000

 

Various locations This project will provide conduits to connect buildings. Those conduits will be the backbone of our campus’ data communication net work. Electrical distribution system will also be up-grated/ consolidated.

Supplemental Request

(System wide)

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

10
JH

Jan
24

Modification for the Handicapped Phase 2

$4,284,000

Ronald H. Nagata AIA, Inc. (Consultant)

Main Campus wide site access corrections, College of Ag., EKH, Life Science, Theater Correct accessibility problems noted on the survey.

Design Initiated.

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

11
LC

Jan 31

Modification for Accessibility Phase 3

$3,031,000

(Consultant selection process)

Various locations Project will improve accessibility improvement to a number of buildings and site improvements.

Project initiation

(System wide)

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

12
SK

Jan
24

(PORK) - Pacific Aquaculture and Coastal Research Center

$500,000 (State)

$1,800,000 (Fed) matching funds

Old County Sewer Plant, Keaukaha Project will provide Aquaculture teaching and research facilities

Project initiation

(System wide)

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

13
JH

Jan
24

Manono Sewer & Fire Protection

$2,000,000

Wesley Segawa and Associates (Consultant)

Campus Wide Manono Campus This project will connect existing facilities in Manono Campus to County Sewer lines, and up-grade fire protections, which are necessary for further construction/ renovations in Manono Campus.

Design/

Fall 2000 to Spring 2002

CC will request construction fund.

(System wide)

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

14
LC

Jan 31

Haw CC Science Lab Renovation

$350,000

 

Campus Wide Manono Campus The project will provide renovation to a Science Lab in Haw CC Campus. (This project is funded through Community College System. Our office will provide substantial support - from budget to construction management.)

Project Initiation

(System wide)

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

15
LC

Jan 31

Haw CC Shop Renovation

$800,000

Haw CC various shops The project will provide renovation to existing shops in Haw CC Campus. (Project funded through CC)

Project Initiation

(System wide)

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

18
JH

Jan 24

Energy Conservation Performance Contract

$5,000,000

Johnson Controls, Inc.

Campus Wide AC upgrades, lighting retrofit and maintenance contract

Construction Completed

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

20
LC

Jan 31

Kawili Street Development

Over $50,000,000

 

Kawili Street This project will provide Student Dormitory, University related commercial and other amenities.

 

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

21
L

Jan 31

Marine Sciences Building

$3,000,000

$290,000

CDS International

(Consultant)

Marine Sciences Building Project will provide a new Marine Sciences Building, with special labs, classroom, faculty offices and support facilities.

Design/

Summer 2000 to Summer 2001

(Pork)

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

22
LC

Jan 31

Classroom Office Building

$19,000,000

Kajioka Yamachi/ Architects, Inc. (Consultant)

Classroom Office Building Project will provide a major classrooms, offices, labs, and support facilities to bring UH Hilo into the next Century.

Final Design/

Summer 2000 to Spring 2002

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

23
JH

Jan 24

Welding Shop Renovation

$800,000

Kajioka Yamachi Architects (Consultant)

Central Construction, Inc. (Contractor)

Old Welding Shop Building 388 Manono Campus Renovate shop to classrooms and offices

Construction completed

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

24
SK

Jan 24

(Supplemental CIP) - Multi-Purpose Sports, Recreation and Conference Complex - Feasibility and Marketing Study

$100,000

Group 70 International, Inc. (Consultant)

Main Campus Feasibility and Marketing Study

 

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

25
SK

Jan 24

(PORK) - Multi-Purpose Sports, Recreation and Conference Complex - Planning Study

$300,000

Group 70 International, Inc. (Consultant)

Near Athletic Complex, Main Campus Master Planning concept for a Multi-Purpose Complex

Project Initiated by Eugene Imai to Gov. Waiting for approval.

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

26
LC

Jan 31

(PORK) - Softball Field Improvement

$325,000

Women’s softball field This project will provide planning and light improvements to softball field.

To be lapsed by Governor.

(Pork)

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

27
LC

Jan 31

Bank of Hawaii

$350,000

$625,000

$1,000,000

Ron Nagata AIA, Inc (Consultant)

Downtown Hilo This project will provide renovation to Bank of Hawaii building in Downtown Hilo as University’s Business Incubator.

Project Initiation

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

28
LC

Jan 31

(PORK) (Supplemental CIP) -Renovation and Addition of Student Services Building

$200,000

Planning

Urban Works (Consultant)

($1,000,000 Design)

Student Services Building This project will provide addition to existing Student Services building to consolidate Student Services functions and to house Chancellor’s Office and other related Administrative functions.

Project initiation/

Supplemental Request

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

29
LC

Jan 31

(Supplemental CIP) - Haw CC Campus Parking Improvement

$800,000

 

  The project will provide parking and drainage improvement in Haw CC Campus.(Project funded through CC System.)

Supplemental Request

(System wide)

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

30
LC

Jan 31

(Supplemental CIP ) - Flood Control Chanel

$75,000 Planning

  This project will provide flood study and allow the University to obtain up to 20 acres of land currently in the Flood Control Channel.

Supplemental Request

(System wide)

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

31
LC

Jan 31

(Supplemental CIP) - University Park - Two (above Komohana)

$350,000 Planning

350 acres site above Komohana This project will provide master plan, and EIS to 350 plus acres of land above Komohana.

Supplemental Request

# Project/Cost/ Consultant/Contractor Location/ Building Project Scope Estimated Schedule

32
SK

Jan 24

Pump and well at Panaewa Farm

$509,000

(Consultant selection process)

Panaewa Ag Farm Design of a new pump and well and water distribution.

Pork funding has not been released.

Project initiated. Waiting for funding to be released.

Consultant Selection Process

 