Project Information

UH Hilo Home > Faculty and Staff > Facilities Planning & Construction

Emergency Back-Up Generators

This project will provide Emergency Backup Power for critical building systems and operational functions in the event of short term and long term power outages.

Project Code: - UHH-2013-313

Approximate Cost:

Funds Approximate Cost
Planning/Design $0.00
Construction/Equipment $3,400,000.00
Total: $3,400,000.00

Consultant(s): MK Engineering, LTD

Project Manager: Ted LeJeune

Construction Manager: to be determined

Contractor(s): to be determined

Affected Area(s): Campus Wide

Estimated Construction Time: June 2015 to December 2015

Last Updated: December 2nd, 2014 12:56pm

Note: The information above is subject to change. Please contact the Facilities Planning & Construction Office for current information.