This project will replace the roof of Wentworth Hall.

Project Code: - UHH-2014-401

Approximate Cost:

Funds Approximate Cost
Planning/Design $100,000.00
Construction/Equipment $735,000.00
Total: $835,000.00

Consultant(s): Awa & Associates, LLC

Project Manager: Michael Murakami

Construction Manager: Engineering Partners

Contractor(s): Certified Construction, Inc.

Affected Area(s): Wentworth Hall View Map View Map

Estimated Construction Time: May 2016 to September 2016

Last Updated: January 12th, 2016 7:51am