Emergency Shelters for Student Housing

Project will retrofit the ground floor of Hale Kauanoe for use as an emergency shelter.

Project Code: - UHH-2013-310

Approximate Cost:

Funds Approximate Cost
Planning/Design $350,000.00
Construction/Equipment $2,800,000.00
Total: $3,150,000.00

Consultant(s): Richard Matsunaga & Associates

Project Manager: Lo-Li Chih

Construction Manager: Bowers + Kubota

Contractor(s): Stan's Contracting, Inc.

Affected Area(s): Hale Kauanoe View Map View Map

Estimated Construction Time: May 2016 to May 2017

Last Updated: August 12th, 2016 3:11pm