Project Information

UH Hilo Home > Faculty and Staff > Facilities Planning & Construction

Campus Wide Lead Paint Survey

This project includes the sampling, testing and reporting of possible lead containing building materials on the UHH Campuses. It also includes the preparation of a searchable database for integration with the building inventory system.

Project Code: - UHH-2013-309
Approximate Cost:
Funds Approximate Cost
Planning/Design $110,000.00
Construction/Equipment $0.00
Total: $110,000.00
Consultant(s): Environet
Project Manager: Ted LeJeune
Construction Manager:
Contractor(s):
Affected Area(s): Entire Campus
Status: Complete
Estimated Construction Time: August 2013 to December 2013
Last Updated: February 13th, 2014 11:43am

Note: The information above is subject to change. Please contact the Facilities Planning & Construction Office for current information.