Campus Security & Emergency Operations Center

This project includes the construction of an addition to the UCB that will house the Campus Security and Safety Offices. It also includes the creation of two flex space Emergency Operations Centers within UCB. Structured cabling improvements will be made to 30 structures.

Project Code: - UHH-2012-212

Approximate Cost:

Funds Approximate Cost
Planning/Design $375,000.00
Construction/Equipment $5,500,000.00
Total: $5,875,000.00

Consultant(s): Fleming & Associates, LLC

Project Manager: Ted LeJeune

Construction Manager: to be determined

Contractor(s): to be determined

Affected Area(s): West side of UCB & Various Buildings

Estimated Construction Time: May 2014 to October 2015

Last Updated: February 13th, 2014 11:24am