Project Information

UH Hilo Home > Faculty and Staff > Facilities Planning & Construction

Campus Security & Emergency Operations Center

This project includes the construction of an addition to the UCB that will house the Campus Security and Safety Offices. It also includes the creation of two flex space Emergency Operations Centers within UCB. Structured cabling improvements will be made to 30 structures.

Project Code: - UHH-2012-212
Approximate Cost:
Funds Approximate Cost
Planning/Design $375,000.00
Construction/Equipment $5,500,000.00
Total: $5,875,000.00
Consultant(s): Fleming & Associates, LLC
Project Manager: Ted LeJeune
Construction Manager:
Contractor(s):
Affected Area(s): West side of UCB & Various Buildings
Status: Construction Bids Received on 2-12-2014
Estimated Construction Time: May 2014 to October 2015
Last Updated: February 13th, 2014 11:24am

Note: The information above is subject to change. Please contact the Facilities Planning & Construction Office for current information.