Campus Security Improvements Phase 1

The project includes data network improvements, new video surveillance system and blue light call stations expansion and improvements.

Project Code: - UHH-2011-118
Approximate Cost:
Funds Approximate Cost
Planning/Design $475,000.00
Construction/Equipment $4,600,000.00
Total: $5,075,000.00
Consultant(s): Newcomb & Boyd
Project Manager: Ted LeJeune
Construction Manager: Engineering Partners
Contractor(s): GW Construction
Affected Area(s): Campus Wide
Status: Processing Contract Award.
Estimated Construction Time: March 2014 to September 2014
Last Updated: February 13th, 2014 11:33am

Note: The information above is subject to change. Please contact the Facilities Planning & Construction Office for current information.