Emergency Back-up Generator

Planning for the installation of Back-up Electrical Generators for Critical University Systems

Project Code: - UHH-2011-116
Approximate Cost:
Funds Approximate Cost
Planning/Design $400,000.00
Construction/Equipment $3,499,000.00
Total: $3,899,000.00
Consultant(s): MK Engineering, LTD
Project Manager: Ted LeJeune
Construction Manager:
Contractor(s):
Affected Area(s):
Status: Preparing Design Contract
Estimated Construction Time: August 2013 to August 2014
Last Updated: March 15th, 2013 2:53pm