Project Information

UH Hilo Home > Faculty and Staff > Facilities Planning & Construction

Water Infrastructure Improvements

This project will provide a well and water infrastructure to meet UH Hilo development needs.

Project Code: - UHH-2010-024
Approximate Cost:
Funds Approximate Cost
Planning/Design $400,000.00
Construction/Equipment $2,700,000.00
Total: $3,100,000.00
Consultant(s): Okahara & Associates, Inc.
Project Manager: Lo-Li Chih
Construction Manager: SSFM
Contractor(s): GW Construction
Affected Area(s):
Status: Construction
Estimated Construction Time: July 2012 to December 2014
Last Updated: February 18th, 2014 3:11pm

Note: The information above is subject to change. Please contact the Facilities Planning & Construction Office for current information.