Water Infrastructure Improvements

This project will provide a well and water infrastructure to meet UH Hilo development needs.

Project Code: - UHH-2010-024

Approximate Cost:

Funds Approximate Cost
Planning/Design $400,000.00
Construction/Equipment $2,700,000.00
Total: $3,100,000.00

Consultant(s): Okahara & Associates, Inc.

Project Manager: Lo-Li Chih

Construction Manager: SSFM

Contractor(s): GW Construction

Affected Area(s): to be determined

Estimated Construction Time: July 2012 to August 2015

Last Updated: August 28th, 2014 3:04pm