Living, Learning Community, Phase II

This project will provide addition to Hale Kanilehua as the second phase of the Living, Learning Community project.

Project Code: - UHH-2011-123

Approximate Cost:

Funds Approximate Cost
Planning/Design $350,000.00
Construction/Equipment $3,100,000.00
Total: $3,450,000.00

Consultant(s): Architects Pacific, Inc.

Project Manager: Brenda Hamane

Construction Manager: John Dill - Rider Levett Bucknall

Contractor(s): Isemoto Contracting Co., Ltd.

Affected Area(s): Hale Kanilehua View Map View Map

Estimated Construction Time: June 2013 to December 2014

Last Updated: August 28th, 2014 3:20pm