Project Information

UH Hilo Home > Faculty and Staff > Facilities Planning & Construction

Athletic Repairs & Improvements

Various repairs and Improvements to the Athletic Facilities.

Project Code: - UHH-2011-115
Approximate Cost:
Funds Approximate Cost
Planning/Design $150,000.00
Construction/Equipment $1,000,000.00
Total: $1,150,000.00
Consultant(s): Pacific Architects
Project Manager: Lo-Li Chih
Construction Manager: John Dill - Rider Levett Bucknall
Contractor(s): Central Construction, Inc.
Affected Area(s): Athletics View Map View Map
Status: Prefinal Design Phase
Estimated Construction Time: July 2013 to May 2014
Last Updated: February 18th, 2014 3:16pm

Note: The information above is subject to change. Please contact the Facilities Planning & Construction Office for current information.