Project Information

UHH Home > Faculty and Staff > Facilities Planning & Construction

Off-Site Sewer Improvements Part B - Kawili St

This project will provide for increased Sanitary Sewer capacity for future Projects.

Project Code: CIP - UHH-2006-609B
Approximate Cost:
Funds Approximate Cost
Planning/Design $165,000.00
Construction/Equipment $1,100,000.00
Total: $1,265,000.00
Consultant(s): Engineering Partners
Project Manager: Ted LeJeune
Construction Manager: Engineering Partners
Contractor(s): Wm. C Loeffler Const.
Affected Area(s): Kawili Street (see Map) View Map View Map
Status: Under Construction
Estimated Construction Time: May 2009 to January 2010
Last Updated: November 13th, 2009 2:38pm

Note: The information above is subject to change. Please contact the Facilities Planning & Construction Office for current information.