Project Information

UHH Home > Faculty and Staff > Facilities Planning & Construction

Campus Wide ADA & Related Improvements

This project will provide campus wide ADA & related improvements. The project will be constructed in two (2) phases.

Project Code: R&M - UHH-2007-710
Approximate Cost:
Funds Approximate Cost
Planning/Design $350,000.00
Construction/Equipment $3,000,000.00
Total: $3,350,000.00
Consultant(s): CDS International
Project Manager: Michael Murakami
Construction Manager:
Contractor(s):
Affected Area(s): Campus wide
Status: Design
Estimated Construction Time: September 2010 to November 2011
Last Updated: November 20th, 2009 2:37pm