Hawaiian Language College
Hawaiian Language College
| CIP - UHH-2005-347 | |||||||||
| Approximate Cost: |
|
||||||||
| Consultant(s): | SSFM International | ||||||||
| Project Manager: | Project managed by OCI, Contact Maynard Young (808) 956-4071 | ||||||||
| Construction Manager: | Project Management, Inc. | ||||||||
| Contractor(s): | |||||||||
| Affected Area(s): | Project site is above Waiakea Stream adjacent to Nowelo Street |
||||||||
| Jacobsen Construction mobilized and began work on August 1, 2011. Site clearing and grubbing is complete and mass excavation and haul out is underway. Probing and grouting at the building pad began 9 | |||||||||
| August 2011 to December 2012 | |||||||||
| Last Updated: | September 5th, 2012 2:17pm |