Project Information

UH Hilo Home > Faculty and Staff > Facilities Planning & Construction

Hawaiian Language College

Hawaiian Language College

Project Code: CIP - UHH-2005-347
Approximate Cost:
Funds Approximate Cost
Planning/Design $0.00
Construction/Equipment $0.00
Total: $0.00
Consultant(s): SSFM International
Project Manager: Project managed by OCI, Contact Maynard Young (808) 956-4071
Construction Manager: Project Management, Inc.
Contractor(s):
Affected Area(s): Project site is above Waiakea Stream adjacent to Nowelo Street View Map View Map
Status: Jacobsen Construction mobilized and began work on August 1, 2011. Site clearing and grubbing is complete and mass excavation and haul out is underway. Probing and grouting at the building pad began 9
Estimated Construction Time: August 2011 to December 2012
Last Updated: September 5th, 2012 2:17pm

Note: The information above is subject to change. Please contact the Facilities Planning & Construction Office for current information.