Project Information

UHH Home > Faculty and Staff > Facilities Planning & Construction

Portable Bldg for Relocated EKH Offices

Design for portable/modular offices for the relocated offices of the EKH Air Quality Improvement Project.

Project Code: R&M - UHH-2007-703
Approximate Cost:
Funds Approximate Cost
Planning/Design $400,000.00
Construction/Equipment $3,011,415.00
Total: $3,411,415.00
Consultant(s): Ushijima Architects, Inc.
Project Manager: Michael Murakami
Construction Manager: Dan Kaniho
Contractor(s): Isemoto Contracting Co., Ltd.
Affected Area(s): Area north of Welding (Bldg. 324) View Map View Map
Status: Construction
Estimated Construction Time: May 2009 to November 2009
Last Updated: June 9th, 2009 1:55pm

Note: The information above is subject to change. Please contact the Facilities Planning & Construction Office for current information.