Project Information

UHH Home > Faculty and Staff > Facilities Planning & Construction

Re-roof Business Office, New Gym & Various Bldgs

Re-roofing of Buildiings 320A, 320B, 320C, 300 and covered walkways.

Project Code: R&M - UHH-2006-602A
Approximate Cost:
Funds Approximate Cost
Planning/Design $122,072.00
Construction/Equipment $1,600,000.00
Total: $1,722,072.00
Consultant(s): Fung Associates
Project Manager: Ted LeJeune
Construction Manager:
Contractor(s):
Affected Area(s): Business Office, New Gym & Various Bldgs View Map View Map
Status: Out for Bid
Estimated Construction Time: March 2010 to December 2010
Last Updated: November 20th, 2009 2:34pm

Note: The information above is subject to change. Please contact the Facilities Planning & Construction Office for current information.