Planning & Construction Graph

UH Hilo Home > Faculty and Staff > Facilities Planning & Construction

month = Planning month = Construction
2015 2016 2017 2018
08 09 10 11 12 01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04 05 06 07 08
College of Pharmacy Building
UH 09-348
                                                                         
Kawili Street Pedestrian Overpass
UHH 2014-402
    10 11 12 01 02 03 04 05 06 07 08 09 10                                            
OMKM Renovation & Infrastructure Improvements
UHH 2014-407
08 09 10 11                 08 09 10 11 12 01 02 03 04 05 06 07 08                        
Repair/Renovate Old Student Services Building
UHH-2010-013
08 09 10 11                                                                  
Water Infrastructure Improvements
UHH-2010-024
08 09                                                                      
Air Conditioning Improvements at Campus Center (Bldg. 336)
UHH-2011-102
08 09                                                                      
Campus Security Improvements Phase 1
UHH-2011-118
08                                                                        
Living Learning Community, Phase IIB
UHH-2011-123B
08 09                                                                      
Renovate and Repair Old Gym (Bldg. 345D) and Various Buildings
UHH-2012-202
08 09 10 11 12                                                                
Energy Management Improvements
UHH-2012-203
08 09 10 11 12                                                                
Campus Security & Emergency Operations Center
UHH-2012-212
08 09 10                                                                    
AC Improvements at Administration
UHH-2013-304
08                                                                        
AC Improvements at Theater, Phase II
UHH-2013-305
08                                                                        
Hale Kehau Roof Replacement
UHH-2013-308
                  05 06 07 08                                                
Emergency Shelters for Student Housing
UHH-2013-310
                          09 10 11 12 01 02 03 04 05 06 07 08                        
Signage Master Plan & Standards
UHH-2013-311
                                                                         
Emergency Back-Up Generators
UHH-2013-313
08 09 10 11 12                                                                
Reroof Wentworth Hall
UHH-2014-401
                  05 06 07 08                                                
Panaewa Farm Traffic Safety Improvements
UHH-2014-403
  09 10 11 12 01 02 03 04 05                                                      
Kapiolani & Kawili Street Sidewalk & Crosswalk Improvements
UHH-2014-404
  09 10 11 12 01 02 03 04 05                                                      
Replace Flag Pole at Mian Entrance
UHH-2015-508
08 09