Planning & Construction Graph

UH Hilo Home > Faculty and Staff > Facilities Planning & Construction

month = Planning month = Construction
2014 2015 2016 2017
07 08 09 10 11 12 01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04 05 06 07
College of Pharmacy Building
UH 09-348
                                                                         
Kawili Street Pedestrian Overpass
UHH 2014-402
07 08 09 10 11 12 01 02 03 04 05                                                    
OMKM Renovation & Infrastructure Improvements
UHH 2014-407
07 08 09 10 11 12 01 02 03 04 05                                                    
Repair/Renovate Old Student Services Building
UHH-2010-013
  08 09 10 11 12 01 02 03                                                        
Water Infrastructure Improvements
UHH-2010-024
07 08 09 10 11 12                                                              
Campus Wide Elevator Improvements
UHH-2010-030
07 08                                                                      
Air Conditioning Improvements at Campus Center (Bldg. 336)
UHH-2011-102
07 08 09 10 11 12 01 02 03 04 05 06 07 08 09                                            
Athletic Repairs & Improvements
UHH-2011-115
                                                                         
Campus Security Improvements Phase 1
UHH-2011-118
07 08 09                                                                    
Food Service Equipment Replacement, Phase I
UHH-2011-119
07 08                                                                      
Chemical Storage Facility
UHH-2011-121
07 08 09 10 11 12 01 02 03                                                        
Living, Learning Community, Phase II
UHH-2011-123
                                                                         
Renovate and Repair Old Gym (Bldg. 345D) and Various Buildings
UHH-2012-202
07 08 09 10 11 12                                                              
Energy Management Improvements
UHH-2012-203
      10 11 12 01 02 03 04 05 06 07 08 09 10                                          
Covered Plaza Structural Repair
UHH-2012-210
07 08                                                                      
Campus Security & Emergency Operations Center
UHH-2012-212
07 08 09 10 11 12 01 02 03 04 05 06 07 08 09 10                                          
AC Improvements at Administration
UHH-2013-304
                    05 06 07 08                                              
AC Improvements at Theater, Phase II
UHH-2013-305
                      06 07                                                
Hale Kehau Roof Replacement
UHH-2013-308
07 08         01 02 03 04 05 06                                                  
Emergency Shelters for Student Housing
UHH-2013-310
07 08                                                                      
Emergency Back-Up Generators
UHH-2013-313
  08 09 10 11 12 01 02 03                                                        
Panaewa Farm Traffic Safety Improvements
UHH-2014-403
07 08 09 10 11 12 01         06 07 08 09 10 11 12 01                                    
Kapiolani & Kawili Street Sidewalk & Crosswalk Improvements
UHH-2014-404
07 08 09 10 11 12 01 02