Welcome to the University of Hawaiʻi at Hilo's Facilities Planning and Construction web site. Here you may find information on current and future projects. Click on a project title to jump to a detail of that project.

Construction News

EDITH KANAKAOLE HALL RESTROOM CLOSURE

Monday, March 18, 2013, 12:00am

Project Schedule Graph

Graph of current projects

Information of Construction Projects

And sort by: Title Project Code Estimated Construction Time PM CM

Living, Learning Community, Phase I
Project Number: UHH-2011-113
Status: Construction Phase
Estimated Time: 2012-05-01 to 2013-05-01
Description: Renovate Hale Kanilehua for a Living, Learning Community.
Affected areas: Hale Kanilehua View UHH-2011-113 Map (PDF)
Living, Learning Community, Phase II
Project Number: UHH-2011-123
Status: Bidding Phase
Estimated Time: 2013-06-01 to 2014-05-01
Description: This project will provide addition to Hale Kanilehua as the second phase of the Living, Learning Community project.
Affected areas: Hale Kanilehua View UHH-2011-123 Map (PDF)
Repairs & Improvements to Pacific Aquaculture & Coastal Resource Center
Project Number: UHH-2010-004
Status: Bidding
Estimated Time: 2012-05-01 to 2013-05-01
Description: This project involves repairs to two existing Mechanical Buildings in order to provide additional office space at this facility
Athletic Repairs & Improvements
Project Number: UHH-2011-115
Status: Prefinal Design Phase
Estimated Time: 2013-04-01 to 2013-08-01
Description: Various repairs and Improvements to the Athletic Facilities.
Affected areas: Athletics View UHH-2011-115 Map (PDF)
Chemical Storage Facility
Project Number: UHH-2011-121
Status: Consultant Contract
Estimated Time: 2013-08-01 to 2014-08-01
Description: This project will provide a Chemical Storage Building located next to Science and Technology Building.
Affected areas: Science & Technology Building View UHH-2011-121 Map (PDF)
Flood & Drainage Mitigation for Switchgear Building
Project Number: UHH-2010-024
Status: Design
Estimated Time: 2112-07-01 to 2013-05-01
Description: This project will provide a well and water infrastructure to meet UH Hilo development needs. View UHH-2010-024 Map (PDF)
Water Infrastructure Improvements
Project Number: UHH-2010-024
Status: Construction
Estimated Time: 2012-07-01 to 2013-07-01
Description: This project will provide a well and water infrastructure to meet UH Hilo development needs.
Air Conditioning Improvements at Campus Center (Bldg. 336)
Project Number: UHH-2011-102
Status: Design
Estimated Time: 2014-05-01 to 2015-09-01
Description: Work will include replacement of air handling units, replacement of the air cooled chiller plant and modification of the distribution system.
Housing Improvements
Project Number: UHH-2010-029
Status: Construction
Estimated Time: 2012-05-01 to 2013-08-01
Description: Electrical upgrades, replacement of doors/windows, renovation of toilet rooms and roof repairs.
Affected areas: Hale Kanilehua, Hale Kauanoe, Hale Ikena
Improvements to Pacific Aquaculture and Coastal Resource Center (PACRC), Phase II
Project Number: UHH-2011-114
Status: Contract
Description: This project will make improvements to Pacific Aquaculture and Coastal Resource Center (PACRC) facilities at Keaukaha and the Panaewa Research Farm
Food Service Equipment Replacement, Phase I
Project Number: UHH-2011-119
Status: Construction
Estimated Time: 2014-05-01 to 2014-08-01
Description: The project will replace various food service equipment in the Campus Center kitchen.
Relocation of Auxiliary Services
Project Number: UHH-2012-201
Status: Consultant contract
Description: The project will renovate existing buildings at the former Army Reserve facility for Auxiliary Services functions.
Affected areas: Former Army Reserve facility on Lanikaula Street
Renovate and Repair Old Gym (Bldg. 345D) and Various Buildings
Project Number: UHH-2012-202
Status: Design
Description: This project will renovate and repair the Old Gym, (Bldg. 345D), Old Gym - Men's Locker (Bldg. 345F), Old Gym - Women's Locker (Bldg. 345G) and various other buildings.
Student Services Bldg
Project Number: UHH-2000-006
Status: Phase I-Parking Lot is completed. Phase II Student Services Building under construction.
Estimated Time: 2011-04-01 to 2012-07-01
Description: This project will provide addition to existing Student Services building to consolidate Student Services functions and to house Chancellor's Office and other related Administrative functions.PresentationView Presentation
Affected areas: Existing Student Services Parking Lot and adjacent grass area towards Theater. Also portion of Parking Lot between Theater and Kawili Street View UHH-2000-006 Map (PDF)
Hawaiian Language College
Project Number: UHH-2005-347
Status: Jacobsen Construction mobilized and began work on August 1, 2011. Site clearing and grubbing is complete and mass excavation and haul out is underway. Probing and grouting at the building pad began 9
Estimated Time: 2011-08-01 to 2012-12-01
Description: Hawaiian Language CollegePresentationView Presentation
Affected areas: Project site is above Waiakea Stream adjacent to Nowelo Street View UHH-2005-347 Map (PDF)
College of Pharmacy Building
Project Number: UH 09-348
Status: Preliminary phase of design ongoing.
Description: Provide permanent facility for the proposed College of Pharmacy
Affected areas: UH Park - S. Aohoku Street View UH 09-348 Map (PDF)
University Village
Project Number: UH HI 11-006
Status: Ongoing discussion with the University administration to define scope of work and negotiate contract with consultant.
Description: Provide student housing and infrastructure for the University Village.
Affected areas: Approximately 33-acres located along West Kawili Street across the campus main entrance.
Repair/Renovate Old Student Services Building
Project Number: UHH-2010-013
Status: Schematic Design Phase
Estimated Time: 2013-06-01 to 2014-06-01
Description: Repair and renovate existing Student Services Building.
Affected areas: Old Student Services Building View UHH-2010-013 Map (PDF)
Campus Wide Elevator Improvements
Project Number: UHH-2010-030
Status: Pre-Final Design
Estimated Time: 2013-05-01 to 2014-08-01
Description: Renovate various Elevators on Campus.
Emergency Back-up Generator
Project Number: UHH-2011-116
Status: Preparing Design Contract
Estimated Time: 2013-08-01 to 2014-08-01
Description: Planning for the installation of Back-up Electrical Generators for Critical University Systems
Emergency Notification & Synchronized Clock System
Project Number: UHH-2011-125
Status: Awarded
Estimated Time: 2012-08-01 to 2013-05-01
Description: This project will provide campus wide Emergency Notification & Synchronized Clock System.
Affected areas: Campuswide View UHH-2011-125 Map (PDF)